GRP Contractors

Demolition . Asbestos . Dismantling . Site Clearance

Northallerton . Leeds . Bishop Auckland . Cumbria

Demolition Projects


Pyemetrics

GRP Were contracted by SPA Architects Ltd on behalf of Thomas Stevenson to carry out the demolition of the forma Pyemetric Refractories Ltd in Middlesbrough GRP carried out R&D Asbestos Survey, Asbestos Insulation Board removal and demolition of the fire damaged workshops, Floor Slab removal and all hardcore removed from site for recycle.


Halls Construction Services

GRP Were contracted by Halls Construction Services to carry out a number of demolition projects on the former redcar steel works site on Teesside GRP carried out a number of R&D Asbestos Surveys, Asbestos Removal and demolition

  • The controlled demolition of Former Ferro Manganese Crushing Plant
  • The viewing platform on Metals Recovery Site
  • The Former Dispatch Office – South Bank
  • The Former Switch House – South Bank
  • The Former Pumphouse – South Bank
  • The Former Fresh Water Tank – South Bank
  • The Elevated Redundant Tank on Supports – South Bank
  • The Former Switch House – South Bank
  • The Redundant Substation – South Bank
  • The Former Pig Casting Machine Control House – South Bank
  • The Redundant Clevestone Garage Units – South Bank
  • The Redundant Substation – South Bank
  • The Former Maintenance Office & Welfare Buildings – South Bank.
  • Old tarmac plant
  • Chepstow workshops


Church Building - Croxdale

GRP were contracted to carry out the demolition of the former church building at Croxdale. Due to the close proximity of the neighbouring house the building had to have a scaffold erected to allow the building to be demolished by hand.

This was carried out very carefully while maintaining good contact with the neighbour to alleviate any concerns they may have had before and during the work. The stone from the building was recycled where possible and the contract was completed within 4 weeks.


Oswin Grove – Gilling West

Following the flooding of the care home GRP were contracted by Broadacres Housing Association to carry out the demolition and asbestos removal on the now redundant care home.

Care had to be taken due to the close proximity of the residential properties on one side of the property and the water course on the other side. Waste and all plant could only be stored on the higher ground on the south side of the site to avoid it being carried away should the land flood again.

Dust suppression techniques were used to stop dust affecting the residents especially during the crushing of the hardcore which was stockpiled on site for future use. The contact was completed within 12 weeks.

Arriva Bus Depot – Richmond

GRP were tasked with the asbestos removal, demolition and redundant tank removal from the Bus Depot by Broadacres Housing Association. The demolition of the building took place near residential properties and a busy road.

The cement asbestos cladding was removed carefully first before the removal of the portal frame structure. The concrete slab was broken out and crushed on site ready to be used in the construction phase of the work by RBA Moody (Bros) Contractors. The contents of the redundant fuel tanks had to be WAC tested to check what substances they still contained as well as the surrounding soil due to suspicions that the tanks may have leaked slightly. Hydrocarbons were found to have leaked into the soil so it had to be removed from site and disposed of at registered waste disposal site. The holes were then refilled with clean recycled hardcore ready for the construction phase to begin. The contract was completed on time.


Stocks Blocks Leeds

GRP was appointed main contractor by Stocks Blocks, part of Thomas Armstrong Group to safely dismantle block making plant including mixers, finger carts, stacking machines and silos ready for export.

In addition GRP carried out licensed removal of asbestos insulation board (AIB) in accordance with the HSE regulations.

Demolition Dismantling Leeds Yorkshire Asbestos
Stocks Blocks Leeds Demolition Recycling

GRP dismantled portal frame buildings for resale and demolished a variety of structures including concrete ovensand a 30m steel chimney.

The project was completed in a 12 week duration.

Springfield Works Mill Guiseley

GRP completed the hand demolition of a 100ft chimney and subsidiary buildings using mechanical excavators at the former Springfield Works Mill, Guiseley for Chartford Homes.

Springfield Mill Demolition Hand Demolition
Hand demolition excavator GRP West Yorkshire

Retrictions were enforced due to live railway line which ran adjacent to the site and surrounding residential buildings.

GRP recycled all timber waste, brick and hardcore to maintain efforts to minimise the production of waste and landfill materials.

Fenton Service Station Rotherham

GRP were contracted to undertake the demolition of a former ESSO filling station for Fox Construction.

Works incuded the excavation, safe removal and disposal of the fuel storage tanks.

Filling Station Demolition Salvage
Filling Station Tank Removal Hazardous Waste

Working to the requirements of the client ESSO, our method statements hand to be meticulously adhered to whilst maintaining the agreed schedule.

The project was completed in 2 weeks, allowing Fox Construction to deliver the new Tesco Express store on time.


  • Various asbestos removal and disposal on the above buildings


BP registered
Nebosh
ACAD
UKATA
HSE
chas
NDTG
©2024 GRP Contractors Ltd